Progress shows at TPW wind farm

A worker at the TPW wind farm prepares a nacelle to be lifted by a crane.Construction remains on schedule at the Third Planet Windpower, LLC wind farm east of Petersburg.

A total of 16 tower bases and mid-sections were completed by last Friday, June 17, leaving 11 more to finish up that portion of the 27-tower wind farm. Blattner Construction, the construction contractor, has been completing an average of two tor base and mid-sections each day.

All components have now been delivered to the tower sites.

Details in the June 22 Albion News and Petersburg Press Print and Electronic Editions.