Lowell Imus leads a group of Boone Central staff members through the new gym.
Lowell Imus leads a group of Boone Central staff members through the new gym.
Boone Central School staff had an opportunity to tour the new addition portion of the school construction project last Wednesday, March 8.
Lowell Imus, custodian, led the tour of 25 to 30 staff members, starting with the wrestling room and weight/fitness room on the south end.
Most HVAC system components have been installed in these large rooms, where painting is underway on the walls and ceilings. Concrete floors have also been poured.
Locker rooms are located just north of the weight/fitness room. Plumbing has been installed and block work is complete in those rooms. Plumbing has been roughed in.
In the new gym, painting was recently completed, the concrete floor is complete, and HVAC installation is underway.
Details in the March 15 Albion News Print and E-editions.