Concrete roof panels were installed on the arena wash racks last week. A two-inch poured concrete cap will be installed over these panels.
Lights are being installed in the arena area and painting is underway there this week.
In the north offices area, drywall work is mostly complete and painting is underway. Early this week, the suspended ceiling installation began, and epoxy floors were being installed. Restroom partitions and toilets were also being installed.
Fuelberth said construction progress is going well and the structure should be completed by the April 1 target date.
The center will be the site of the Memorial weekend “arama” livestock shows and Boone County Fair events in July.
Many additional events at this facility are expected to be booked.